The web-based CompTIA PK0-005 practice test software can be used through browsers like Firefox, Safari, and Google Chrome. The customers don't need to download or install any excessive plugins or software in order to use the web-based CompTIA PK0-005 Practice Exam format. The web-based PK0-005 practice test software format is supported by different operating systems like Mac, iOS, Linux, Windows, and Android.
CompTIA Project+ Certification is an industry-recognized certification designed for professionals who are interested in project management. CompTIA Project+ Certification Exam certification validates the knowledge and skills of the candidate in project management and helps them to excel in their career. The latest version of the exam, CompTIA PK0-005, was released in March 2021 and is designed to meet the current requirements of the industry.
You may be get refused by so many PK0-005 study dumps in thehe present market, facing so many similar PK0-005 study guide , so how can you distinguish the best one among them? We will give you some suggestions, first of all, you need to see the pass rate, for all the efforts we do to the PK0-005 Study Dumps is to pass . Our company guarantees the high pass rate. Second, you need to see the feedback of the customers, since the customers have used it, and they have the evaluation of the PK0-005 study guide.
CompTIA PK0-005 Certification Exam is an excellent choice for professionals who are involved in managing projects. CompTIA Project+ Certification Exam certification exam is vendor-neutral and covers a wide range of topics related to project management. CompTIA Project+ Certification Exam certification provides candidates with a competitive advantage in the job market and helps them to enhance their career opportunities.
NEW QUESTION # 311
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
Answer: D
Explanation:
Explanation
Monthly feedback and training sessions are the best approach to ensure that the deliverables of a critical business initiative are increasingly adopted and leveraged by the organization over time. Feedback and training sessions are communication and learning activities that provide information and guidance on how to use and benefit from the new processes and technology introduced by the initiative. Feedback and training sessions can help to increase awareness, understanding, acceptance, and adoption of the deliverables among the organization's employees and stakeholders. They can also help to identify and address any issues or challenges that may arise during the implementation and transition phases.
NEW QUESTION # 312
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?
Answer: B
Explanation:
SaaS, or software as a service, is a cloud model that provides on-demand access to ready-to-use, cloud-hosted application software. SaaS is the best solution for the global franchise, because it can unify its operation worldwide by using the same software platform across different locations and devices. Additionally, SaaS can provide operation reports in real time without asking the country franchise manager for these reports, because the cloud service provider manages the data collection, analysis, and presentation in the cloud. SaaS also offers the benefits of scalability, reliability, security, and cost-effectiveness for the global franchise.
SaaS is different from IaaS, or infrastructure as a service, which provides on-demand access to cloud-hosted computing infrastructure, such as servers, storage, and networking. IaaS is not suitable for the global franchise, because it requires the franchise to manage and maintain its own software applications and data on the cloud infrastructure. IaaS also does not provide operation reports in real time, unless the franchise develops its own reporting tools and processes. SaaS is also different from XaaS, or anything as a service, which is a generic term that encompasses various types of cloud services, such as IaaS, PaaS, SaaS, and others. XaaS is not a specific cloud model that the company can suggest to the global franchise, but rather a broad category of cloud offerings. SaaS is also different from PaaS, or platform as a service, which provides on-demand access to a complete, ready-to-use, cloud-hosted platform for developing, running, maintaining, and managing applications. PaaS is not ideal for the global franchise, because it requires the franchise to develop and deploy its own software applications on the cloud platform, which may be more complex and time-consuming than using a ready-made SaaS solution. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 5: Project Scope Management1; CompTIA Project+ Certification Study Guide,
3rd Edition, Chapter 5: Project Scope Management2; IaaS vs. PaaS vs. SaaS3
NEW QUESTION # 313
A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?
Answer: D
Explanation:
This answer is based on the best practice of defining access requirements in project management, which is to identify the roles, responsibilities, and permissions of the project team members and other stakeholders who need to access the project information, resources, and deliverables12. The first step in this process is to assess the resource pool, which is the availability and capability of the human resources that can be assigned to the project34. By assessing the resource pool, the project manager can determine the skills, experience, and security clearance of the potential project team members, as well as their reporting relationships, communication preferences, and expectations56. This information can help the project manager to define the access requirements for each role and stakeholder group, and to assign the appropriate level of access to the project data, documents, tools, and systems78. Reference = CompTIA Project+ Certification Study Guide9, CompTIA Project+ Certification Exam Objectives10, What is Requirements Management?, How to Write Project Requirements, A Guide to Functional Requirements, Project Requirements Management: A Quick Guide, Creating clear project requirements, How to Define Project Roles and Responsibilities
NEW QUESTION # 314
A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?
Answer: B
Explanation:
A proposal is a detailed document submitted by vendors outlining how they will meet project requirements. It helps in assessing vendor solutions and suitability, consistent with CompTIA Project+ procurement and vendor management practices.
NEW QUESTION # 315
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
* Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
* Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
Answer:
Explanation:
See the Explanation for the solution.
Explanation
Part 1:
Change Control Process:
* Consult the RACI matrix.
* Define new requirements and record changes.
* Assess the schedule, risk, and cost.
* Perform a demonstration.
* Obtain a sign off.
* Update and test the deliverable.
* Make an announcement on the company portal.
The change control process is a sequence of steps that helps to manage and document any changes or modifications to a project scope, schedule, cost, quality, or resources. The change control process typically involves the following steps:
* Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI stands for responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify who needs to be involved or informed about the change request and how to communicate with them.
* Define new requirements and record changes. The new requirements and changes are the details of what needs to be modified or added to the project deliverables or objectives based on the customer feedback or request. Defining and recording the new requirements and changes can help to communicate and justify the need and rationale for the change and its implications on the project scope and quality.
* Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that may be affected by the change request. Assessing the schedule, risk, and cost can help to determine the impact and feasibility of the change and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.
* Perform a demonstration. A demonstration is a presentation or show of how the modified or updated deliverable works or meets the customer expectations or requirements. Performing a demonstration can help to validate and verify that the change request has been implemented correctly and effectively and to obtain feedback or approval from the customer or stakeholders.
* Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the change request has been completed successfully and satisfactorily and to close the change control process.
* Update and test the deliverable. The deliverable is the product or service that is produced or provided by the project. Updating and testing the deliverable can help to ensure that it meets the quality standards and criteria and that it works as expected after implementing the change request.
* Make an announcement on the company portal. The company portal is a platform or channel that allows internal communication and collaboration among employees within an organization. Making an announcement on the company portal can help to inform and update other team members or departments about the change request and its outcomes and to share any lessons learned or best practices from the change control process.
Part2:
* Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or
* uncertainties that may affect a project. Updating the risk register can help to capture any new or modified risks that may arise from the change request and to plan and implement appropriate risk responses.
* Schedule:A schedule is a document that shows the planned start and end dates, durations, dependencies, and progress of each task or activity in a project. Updating the schedule can help to reflect any changes or adjustments to the project timeline or milestones that may result from the change request and to monitor and control the project performance and delivery.
* Statement of work:A statement of work (SOW) is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. Updating the SOW can help to document any changes or additions to the project scope or deliverables that may be requested or agreed upon by the customer or stakeholders and to ensure alignment and agreement on what needs to be done and how it will be done.
* Change log:A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. Updating the change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.